Zoning guide

Zoning Feasibility Study: What It Covers, Who Prepares It, and a Sample Report

What a zoning feasibility study (zoning analysis) covers, who prepares one, what it costs and how long it takes, and a full sample study for a 1.1-acre commercial parcel in St. Petersburg, Florida, built from the city code and official GIS.

By Nathan Robinson, Founder, Plotzy Published 16 min read

A zoning feasibility study, also called a zoning analysis or zoning feasibility report, is a written review of what the zoning code and comprehensive plan allow on one parcel, tested against a proposed project. It answers three questions: is the use allowed, how much can be built, and which approvals stand between the site and a building permit. Buyers order one before closing because those answers drive what the land is worth.

This guide covers what a study includes, who prepares it, what it costs, and a full sample study for a real 1.1-acre parcel at 450 34th Street North in St. Petersburg, Florida, built from the city code and official GIS layers as of November 19, 2026.

What does a zoning feasibility study include?

A complete study covers the use, the size of building the rules allow, and the path to approval. These twelve sections are the standard checklist:

SectionQuestion it answersWhere the answer lives
Jurisdiction and designationsWhich code applies, and what district and overlays cover the parcel?City or county GIS, official zoning map
Permitted useIs each use allowed by right, by special approval, or not at all?Use table or use matrix
DensityHow many units per acre?District standards and bonus rules (units per acre calculator)
Floor area ratioHow much floor area?District standards (FAR calculator)
Height and setbacksWhat building envelope fits?District standards, plus the rules on how each is measured
Lot standards and coverageDo lot area, width, and coverage limits work?District standards (lot coverage calculator)
Parking and loadingHow many spaces, and which reductions apply?Parking section and use table
Overlays and hazardsDo overlays, flood zones, or coastal rules change the answer?Overlay chapter, FEMA flood map
Future land use consistencyDoes the comprehensive plan allow the project, or more?Plan text and future land use map
NonconformitiesDo existing uses or buildings carry grandfathered rights or defects?Nonconforming section, city records
Approvals and timelineStaff review, a hearing, or a rezoning? How long?Procedures chapter
Risks and open questionsWhat could change the answer?Pending ordinances, staff interpretations

In Florida, add a Live Local Act check for rental housing on commercial, industrial, or mixed-use land, and a Coastal High Hazard Area check near the coast.

How is it different from a zoning letter or a zoning report?

A zoning letter confirms the district, a lender zoning report checks whether what exists conforms, and a feasibility study tests what you could build.

DocumentWho produces itWhat it tells youTurnaround
Zoning verification letterThe city or countyThe legal zoning, sometimes lawful uses or rebuild statusSet locally. St. Petersburg must issue a property card interpretation, its fuller letter, within 90 days
Zoning report (lender style)Zoning report firmsCurrent zoning, open violations, certificates of occupancy, and as-built conditions compared with an ALTA surveyNV5 says about 2 to 3 weeks for a single site
Zoning feasibility studyLand use attorney, planner, architect, or the buyer's own teamWhat a new project can be under each approval path, and the risksDepends on scope

See how to get a zoning verification letter for city fees and clocks.

Who prepares a zoning feasibility study?

Usually a land use attorney, a planner, or an architect, often working together. On simple sites, a developer's acquisition team does the first pass itself.

  • Land use attorneys interpret unclear code language, write opinion letters, and run rezoning or variance strategy.
  • Planners map designations, check plan consistency, and lay out the approvals path, often after a pre-application meeting with city staff.
  • Architects turn FAR, height, setbacks, and parking into a test fit with a real unit count.
  • Civil engineers check access, stormwater, and utilities, which can cap yield as hard as zoning does.
  • Zoning report firms produce lender conformance reports, not development scenarios.

How much does it cost, and how long does it take?

There is no standard price, because the scope varies. Published figures exist only for narrower products. NV5, a national zoning report firm, says a single-site zoning report averages $700 to $850 including municipal fees and takes about 2 to 3 weeks. A study with an architect's test fit or a legal opinion costs more.

What drives cost and time:

  • Scenarios. By right, bonuses, rezoning, and state-law paths each need their own math.
  • Code clarity. Ambiguous rules need a staff meeting or a formal letter.
  • Add-ons. Survey, title review, test fits, and traffic or utility letters.
  • City clocks. Letters and pre-application meetings run on the city's schedule.
  • Site count. NV5 prices multi-site projects at a base price plus municipal fees.

How to do a site zoning analysis, step by step

  1. Confirm the jurisdiction and parcel boundary at the property appraiser and county GIS. A city address can sit in unincorporated land.
  2. Pull the zoning district, overlays, and future land use category from the official GIS layers. Our guide on finding a property's zoning covers the sources.
  3. Read the use table for every use in the program.
  4. Read the dimensional table and the measurement rules: how lot width, height, and density rounding are defined.
  5. Compute yield: acres times density for units, lot area times FAR for floor area, then height, setbacks, and parking.
  6. Check bonuses and state law, such as workforce housing bonuses, transfer of development rights, and Florida's Live Local Act.
  7. Check plan consistency, and whether the plan supports more through a rezoning. See future land use vs. zoning.
  8. Check nonconformities and prior approvals. See buying property with a nonconforming use.
  9. Map approvals and timeline, and scan council agendas for pending code changes.
  10. Write it up with every finding tied to a code section, plus a list of questions for staff.

Sample zoning feasibility study: 450 34th Street North, St. Petersburg, FL

The study below uses only public records checked on November 19, 2026: the City of St. Petersburg Code (Municode version dated October 21, 2026), the city's zoning and future land use GIS layers, and Pinellas County's parcel, road, flood, and storm surge layers. Owner information is left out. It is a worked example, not legal advice; confirm each finding with the city. Use it as a zoning report example and copy the headings for your own sites.

1. Summary

Program tested: apartments, with optional ground-floor retail.

Bottom line: By right, CCS-1 allows 17 apartments, or 25 with the workforce housing bonus, in a 36-foot building. The Live Local Act path allows up to 90 units if 40 percent are affordable, with staff approval and no hearing. A rezoning to a district the plan already supports would allow 26 units but needs two public hearings. Three questions decide the deal: how the city measures lot width on this three-frontage lot, which height it applies under the Live Local Act, and what Ordinance 655-H changes after its December 3, 2026 hearing.

Do this in Plotzy

Ask the zoning code a question and get a cited answer

Zoning AI reads the ordinance for you. Ask about permitted uses, setbacks, FAR, height, or parking for a specific parcel and get the answer with the section it came from.

  • Two-level zoning on every parcel, nationwide
  • Plain-English answers with section-level citations
  • Filter parcels by zoning before you spend a day on due diligence
See Zoning AI

Free trial

2. Property

ItemFinding
Parcel ID22-31-16-72756-006-0020
Legal descriptionPowers Central Park Sub, Block 6, Lots 2 to 8 and the west 30 feet of Lot 1
Area48,042 sq ft (1.10 acres) by the county GIS polygon; a survey governs
Shape and frontageA rectangle about 378 feet east to west and 127 feet north to south, with streets on three sides: 34th Street North (U.S. 19, a state road) on the east, Dartmouth Avenue North on the north, and 35th Street North on the west
JurisdictionCity of St. Petersburg
Existing improvementsThe county parcel layer shows land value and no building value; confirm on site
NeighborsCCS-1 to the north and south, CCS-2 across 34th Street, NT-2 single-family zoning across 35th Street

3. Designations, overlays, and hazards

LayerFinding
ZoningCCS-1, Corridor Commercial Suburban-1 (Section 16.20.090)
Future land usePR-MU, Planned Redevelopment-Mixed Use
Countywide Plan MapMultimodal Corridor
Activity centerNone on the parcel. The SunRunner Activity Center begins across 34th Street
Other overlaysNone found on the city's SunRunner, transit overlay, special designation, or historic layers
Redevelopment areaSouth St. Petersburg Community Redevelopment Area (relevant to incentives, not zoning limits)
TransitWithin 1/8 mile of high-frequency Route 34 on the city's layer. The nearest SunRunner station, 1st Avenue North at 32nd Street, is about 1,700 feet away
FloodZone X, area of minimal flood hazard, FIRM panel 12103C0218G, effective September 3, 2003
Coastal High Hazard AreaAppears outside it: the county's Category 1 storm surge layer shows no surge at the site

4. Permitted uses (Section 16.10.020.1)

UseCCS-1
Multifamily dwelling, mixed usePermitted
Retail sales and service, indoor restaurantPermitted
General and medical officePermitted
Drive-thru facilityPermitted, with stacking standards
Car wash and detailingSpecial exception

Finding: the program needs no use approval.

5. Dimensional standards (Sections 16.20.090.5 and 16.20.090.6)

The parcel is a "medium lot" (1.0 to 2.0 acres) under the CCS tables.

StandardCCS-1 ruleApplied here
Base density15 units per acre17 units (1.103 acres times 15 is 16.54, rounded up under Section 16.60.010.2.D)
Workforce housing bonusPlus 8 units per acre25 units; the bonus units must be workforce housing under the city program
Nonresidential FAR0.55, plus 0.2 with workforce housing26,423 sq ft, or 36,032 sq ft with the bonus
Maximum impervious surface0.85 of the site40,836 sq ft
Maximum height36 feet (48 feet over 2 acres)36 feet
Minimum lot width200 feet for a medium lotDepends on how width is measured (risk 1)
Street setbacks20 feet minimum, 80 feet maximumOn all three street sides
Interior side and rear20 feet residential next to residential; 10 feet side and 20 feet rear for nonresidential next to nonresidential; 35 feet for nonresidential next to residentialSouth line

The mixed-use trap. For residential-only buildings, density governs and the FAR applies to nonresidential floor area (note to Section 16.10.020.2). But on PR-MU land, Section 16.50.200.3.1.C counts residential and nonresidential floor area together in a mixed-use building. Adding a shop caps the whole building at 0.55 FAR, about 26,400 sq ft, unless a bonus or exemption applies.

6. Development yield by path

PathUnitsHeightApproval
A. By right1736 feetStaff review
B. Workforce housing bonus2536 feetStaff review, under the city's workforce housing program
C. Missing middle bonusUp to 33 (30 per acre)NTM-1 building standardsConfirm the route with staff. The plan allows it only on a major street outside the Coastal High Hazard Area, and it cannot combine with path B
D. Rezone to CCT-1 or CRS-226 (24 per acre)Per the new districtCommission hearing and City Council ordinance; no plan amendment, because both districts are listed as compatible with PR-MU
E. Live Local Act90, with 36 affordable at or below 120 percent of area median income for 30 yearsAt least the tallest allowed within 1 mile, or 3 stories (risk 2)Staff decision after a 30-day comment period; FAR up to 6.0 and lot coverage up to 100 percent

The plan ceiling is 24 units per acre, about 26 units, or 30 per acre for missing middle housing. Beyond that, only path E works without a plan amendment, and Section 16.60.010.2.E bars density variances.

7. Parking (Section 16.10.020.1 and Section 16.40.090)

  • Ratios (suburban tier): 1.25 spaces per apartment over 750 sq ft (up to two bedrooms, plus 0.5 per extra bedroom), 0.75 per apartment of 750 sq ft or less, 1 per 200 sq ft of retail, 1 per 150 sq ft of restaurant.
  • Path A: 17 two-bedroom units need 21 spaces. The 10 percent reduction for sites within 1/8 mile of a high-frequency route brings that to 19.
  • Path E: 90 units need 68 to 113 spaces before reductions, depending on unit size. The statute adds a 15 percent reduction on request within 1/4 mile of an accessible transit stop. On 1.1 acres, that count likely means structured parking, which belongs in the cost model.
  • Not available: the parking exemption within 1/4 mile of a bus rapid transit station. The nearest station is too far.

8. Future land use consistency

PR-MU allows mixed use up to a 1.25 FAR and 24 units per net acre, and Section 16.10.020.2 lists CCS-1 as a compatible district. Florida law requires development orders to be consistent with the plan (section 163.3194). Here the zoning, at 15 units per acre, is the binding limit, which is why path D is plausible. The newest plan copy found is effective January 2022; later amendments may not be in it. See the St. Petersburg future land use guide.

9. Existing conditions and nonconformities

The county layer shows no building value, so existing rights probably matter little. If a building or use is kept, note that a nonconforming use loses its status after a year unoccupied (Section 16.60.030.1). A property card interpretation states the legal units and uses (Section 16.70.070.1.1).

10. Approvals and timeline

StepCodeClock
Pre-application conferenceSection 16.70.010.1; Section 17.5-112 for Live LocalNot stated
Site plan reviewDevelopment Review Commission only above 250,000 sq ft in CCS, or above 60 units in the Coastal High Hazard Area (Section 16.70.040.1.4)Below that, staff review
Live Local Act approvalMailed notice within 300 feet, posted sign, then comment period (Section 17.5-115)30 days minimum; approval valid 3 years, with up to two 2-year extensions (Section 17.5-119)
RezoningNotice of intent 10 days before filing; commission hearing; Council ordinance (Section 16.70)Hearing within 90 days of a complete application
Driveway on 34th StreetThe state transportation department regulates connections to the state highway system (section 335.182)Separate permit

See how long rezoning takes and impact fees for what comes after zoning.

11. Risks and open questions

  1. Lot width. Width is measured between the side lot lines (Section 16.60.010.4). On a corner lot, the front faces the street with the lesser dimension, but combining platted lots without replatting does not change the frontage (Section 16.60.010.8.1). Measured from 34th Street, the width is about 127 feet, under the 200-foot medium-lot minimum; from Dartmouth Avenue, about 378 feet. The code does not say plainly whether the width rule binds an existing combined lot. Ask in writing.
  2. Live Local height. The statute bars a height limit below the tallest currently allowed for a commercial or residential building within 1 mile, or 3 stories. Across 34th Street, CCS-2 parcels sit in the SunRunner Activity Center, where the CCS table allows 84 feet on lots over 2 acres; the parcel at 401 34th Street North is 2.27 acres. The table also has a 72-foot row for the Central Avenue Corridor Activity Center, and the code has not yet been updated to the SunRunner name, so the city may read the figure as 72 feet. Either way, Section 17.5-111(f)(4) says commercial-district projects follow the underlying district standards. Ask which governs. The single-family height cap does not appear to apply: the NT-2 lots are across 35th Street, and "adjacent" excludes parcels separated by a public road.
  3. Ordinance 655-H. City Council set a December 3, 2026 hearing on an ordinance that raises maximum densities and intensities in the CCT, CCS, and RC districts outside the Coastal High Hazard Area. It also raises maximum building heights and moves activity center references to the SunRunner name, and adds a footnote on the countywide multimodal corridor subcategories; this parcel's countywide category is Multimodal Corridor. Rerun the yield after the vote.
  4. Mixed-use floor area. Retail shrinks the building under Section 16.50.200.3.1.C.
  5. Access. A driveway on U.S. 19 needs state approval, and side-street access on 35th Street faces the homes to the west.
  6. Neighbors. Single-family homes across 35th Street will get notice on any path.
  7. Data limits. GIS acreage is not a survey, and the flood finding comes from the county's copy of FEMA's flood data dated December 22, 2025.

12. Recommended next steps

  1. Order an ALTA survey and title commitment.
  2. Book a pre-application meeting and ask about risks 1 to 3.
  3. Commission a test fit for paths A, B, and E.
  4. Request a zoning letter confirming the district and lot status.
  5. Rerun this study after the December 3 hearing.

How do teams run zoning analysis across many sites?

The sample above draws on more than a dozen code sections and over ten GIS layers for one parcel. Teams screening dozens of sites a month can automate the first pass: pull designations, compute yields for each path, flag state-law options, and cite the sections, with a person reviewing the judgment calls. See AI zoning analysis for how that workflow is built. St. Petersburg is one of the Florida places where Plotzy has the zoning map and code loaded parcel by parcel. In Plotzy, filter parcels by zoning designation and lot size, and ask Zoning AI (Production plan and up) "What density, height, and setbacks apply to this parcel?" for an answer with the code section cited.

Frequently asked questions

What is a zoning analysis?

A review of a parcel's zoning district, permitted uses, and dimensional limits to estimate what can be built. A zoning feasibility study applies that analysis to a specific project and adds approvals, timeline, and risks.

Is a zoning verification letter enough for due diligence?

Rarely on its own. It confirms the district but does not test your project. Pair it with a study, and in St. Petersburg consider a property card interpretation, which states legal units and uses.

How long does a zoning feasibility study take?

It depends on scope. NV5 quotes about 2 to 3 weeks for a single-site zoning report, and city letters run on their own clocks, up to 90 days for a St. Petersburg property card interpretation.

Can zoning allow less than the future land use map?

Yes. The plan category sets a ceiling and zoning is often lower, as in the sample: 15 units per acre under CCS-1 against 24 under PR-MU. Closing that gap takes a rezoning, without a plan amendment when the target district is listed as compatible.

Does Florida's Live Local Act override zoning in a feasibility study?

For qualifying rental projects on commercial, industrial, or mixed-use land, it sets floors on density, FAR, and height and requires staff approval. Other local rules, including setbacks and parking, still apply. Model it as a separate path.

Sources

The codes, statutes, maps, and agency documents below were checked on November 19, 2026. Codes and maps change often, so confirm the current version before relying on any detail. This page is general information, not legal advice.

Related reading