Zoning guide
Florida Comprehensive Plan Amendments: Small-Scale vs. Large-Scale, Process, and Timelines
How Florida's consistency rule makes a rezoning above the future land use category wait for a plan amendment, how small-scale and large-scale amendments work under sections 163.3187 and 163.3184, how long each takes, and how SB 180 and the Live Local Act change the picture.
In Florida, a rezoning cannot go beyond what the comprehensive plan's future land use category allows. A project that needs more density, more intensity, or a use the category does not include first needs a comprehensive plan amendment changing the parcel's designation. State law offers two main tracks: a small-scale amendment for map changes of 50 acres or fewer, with one adoption hearing, and the expedited state review process for everything else, with two hearings and state agency comments in between.
Why a rezoning can need a plan amendment first
Section 163.3194(1) requires all development orders and land development regulations to be consistent with the adopted plan. A rezoning is both: section 163.3164 lists rezoning in the definitions of land development regulations and development permits. Under section 163.3194(3)(a), an approval is consistent only if its uses, densities, and intensities are compatible with and further the plan.
So when the zoning you want is above the future land use designation, the designation has to change first or at the same time. Section 163.3184(12) requires the local government, at the applicant's request, to consider the rezoning alongside the plan amendment, with the rezoning contingent on the amendment taking effect. The future land use vs. zoning guide explains when a rezoning alone is enough.
Small-scale vs. large-scale at a glance
"Large-scale" is the common name for an amendment that does not qualify as small-scale. The statute calls the default track the expedited state review process.
| Feature | Small-scale amendment | Large-scale amendment |
|---|---|---|
| Statute | Section 163.3187 | Section 163.3184(3) |
| Size | 50 acres or fewer | Any size |
| What it changes | The map, plus directly related text | The map, the text, or both |
| Governing body hearings | One adoption hearing | Transmittal hearing and adoption hearing |
| State review | None before it takes effect | Agency comments within 30 days of transmittal |
| Takes effect | 31 days after adoption, if not challenged | 31 days after the state finds the adopted package complete, if not challenged |
| Challenge window | 30 days after adoption | 30 days after adoption for affected persons |
Small-scale rules
Under section 163.3187, a small-scale development amendment must involve a use of 50 acres or fewer and only a site-specific change to the future land use map, though text changes that relate directly to the map change and are adopted with it are allowed. The site cannot be in an area of critical state concern, except for certain affordable housing projects. The acreage limit doubles for a site in a rural area of opportunity. The amendment needs only one public hearing before the governing body, an adoption hearing.
Local governments run their own versions inside that ceiling, so check the local threshold. Tampa and Hillsborough County use 50 acres, according to Plan Hillsborough's plan amendment page. Orange County's future land use amendment page labels any amendment of 10 acres or more as large-scale. The city pages on the future land use hub cover local amendment rules.
Large-scale rules
Under section 163.3184(3), the governing body holds a first hearing and transmits the amendment to state and regional reviewing agencies. State agencies may comment only on adverse impacts to important state resources and facilities, and comments must reach the local government within 30 days. The local government then has 180 days after receiving comments to hold the adoption hearing, or the amendment is deemed withdrawn. The adopted package goes to FloridaCommerce, the state land planning agency, within 30 working days. The amendment takes effect 31 days after the agency notifies the local government that the package is complete, unless it is challenged.
A third track, state coordinated review under section 163.3184(4), covers special cases such as areas of critical state concern, sector plans, and plan updates after the seven-year evaluation. The state issues a report within 60 days. Miami's 2024 plan update followed this route: the state report came December 22, 2023, the City Commission adopted on March 14, 2024, and it took effect May 9, 2024, according to the city's Envision 2035/2045 page.
What it can be used for today
Check a parcel's current zoning
The future land use map shows where a city is headed. Zoning decides what you can build now. Zoning AI reads the ordinance for a specific parcel and answers questions about permitted uses, setbacks, FAR, height, or parking, with the section it came from.
- Plain-English answers with section-level citations
- Filter parcels by zoning before you spend a day on due diligence
- Owner, lot size, and last sale next to the zone
Free trial
The process step by step
- Pre-application meeting. Tampa requires one at least 7 days before the filing deadline, per the City of Tampa Plan Amendment Procedures Manual.
- File in the right cycle. Many jurisdictions take map amendments only on set dates. Tampa's deadlines are February 1, May 1, August 1, and November 1. Hillsborough County's are January 1, April 1, July 1, and October 1, per its procedures manual. Orange County runs large-scale amendments in two cycles a year.
- Staff review. Staff test the request against plan policies and infrastructure capacity. Orange County also requires a community meeting.
- Local planning agency hearing. Section 163.3174(4)(a) requires the local planning agency to hold at least one public hearing before recommending.
- Governing body hearing or hearings. One for small-scale, two for large-scale, under section 163.3184(11).
- Effective date. Count 31 days, and longer if there is a challenge.
How long it takes
Orange County's 2026 schedule gives concrete numbers. A small-scale application due March 6, 2026 was scheduled for a June board hearing and a July effective date, about four months. The first large-scale cycle took applications by March 13, 2026, with transmittal around July, adoption around November, and an expected effective date in January 2027, about ten months. The county's fees are $3,529 for small-scale and $6,228 for the regular cycle.
Add time for a countywide layer. In Pinellas County, a change to the Countywide Plan Map category adds hearings before Forward Pinellas and the Countywide Planning Authority, because local plans must be consistent with the countywide plan under Chapter 2012-245, Laws of Florida. Broward County has a similar layer through its Planning Council. Tampa also bars refiling a denied application for 12 months. For the zoning half of the timeline, see how long rezoning takes.
Challenges
Any affected person can file a petition with the Division of Administrative Hearings within 30 days after adoption, under sections 163.3187(5) and 163.3184(5). Affected persons include residents, businesses, and owners of property abutting a parcel whose future land use map designation is changing. In a challenge by an affected person, the amendment is upheld if the local government's finding of compliance is fairly debatable, a deferential standard. A timely challenge delays the effective date until a final order.
SB 180 limits through October 1, 2027
Section 28 of SB 180, Chapter 2025-190, bars each county named in the federal disaster declarations for Hurricanes Debby, Helene, and Milton, and each city in those counties, from proposing or adopting more restrictive or burdensome comprehensive plan amendments, land development regulations, or review procedures before October 1, 2027. Violations are void, and residents and business owners can sue. The rule applies retroactively to August 1, 2024. A Senate staff analysis notes that all 67 counties appear in at least one declaration, so it applies statewide. Two 2026 bills to narrow it, SB 218 and SB 840, died in the House.
For applicants, two points matter. First, an amendment initiated by a private party on property it owns can still be enforced, under section 28(2), so an owner-led future land use change remains available. Second, local governments cannot add more burdensome amendment procedures or adopt more restrictive plan changes, such as downzonings, until the window closes. Orange County's Vision 2050 shows the effect: the state found the plan null and void in July 2025, and the county's September 29, 2026 readoption lets private applicants opt into the older Destination 2030 designations until October 1, 2027, according to Central Florida Public Media. See the Orange County future land use page.
The Live Local Act skips the amendment
For qualifying projects, the Live Local Act removes the need for a plan amendment. Under section 166.04151(7) and section 125.01055(7), a multifamily or mixed-use project on land zoned commercial, industrial, or mixed use, with at least 40 percent of units affordable rentals for 30 years, cannot be required to obtain a land use change or comprehensive plan amendment for the authorized height, zoning, and density. It must be approved administratively if it is otherwise consistent with the plan, except for the plan's limits on density, floor area ratio, height, and land use. The project stays a conforming use after the subsection expires on October 1, 2033, notwithstanding the future land use designation.
Frequently asked questions
What is a small-scale comprehensive plan amendment in Florida?
It is a change to the future land use map for a site of 50 acres or fewer, with no text changes other than those directly tied to the map change. It needs one adoption hearing and no state review, and it takes effect 31 days after adoption if no one challenges it. Local thresholds can be lower.
How long does a future land use amendment take in Florida?
It depends on the local filing cycle and hearing calendar. On Orange County's 2026 schedules, a small-scale amendment took about four months from filing to effect and a large-scale amendment about ten months. A challenge, a countywide plan layer, or a continued hearing adds time.
Can I file the rezoning and the plan amendment together?
Yes. Florida law requires the local government to consider the rezoning alongside the plan amendment at the applicant's request, and the rezoning only takes effect if the amendment does. Many jurisdictions schedule both for the same hearings.
Does SB 180 stop owners from changing their future land use?
No. Section 28 limits amendments that are more restrictive or burdensome, and it expressly allows enforcement of amendments initiated by a private party on its own property. It mainly limits local governments from tightening plans or procedures before October 1, 2027.
Sources
The statutes, bills, and agency documents cited on this page were checked on November 15, 2026. Florida's growth management laws are amended almost every session, so confirm the current text before relying on any detail. This page is general information, not legal advice.
- Florida Statutes 163.3187. Small-scale amendment criteria, hearing, effective date, and challenges.
- Florida Statutes 163.3184. Expedited and state coordinated review, hearings, challenges, and concurrent zoning.
- Florida Statutes 163.3194, 163.3164, and 163.3174. The consistency rule, definitions, and local planning agency hearing.
- Florida Statutes 166.04151 and 125.01055. Live Local Act land use provisions.
- Florida Senate: CS/CS/SB 180 (2025), SB 218 (2026) with its Judiciary Committee analysis, and SB 840 (2026). Section 28, its statewide reach, and the 2026 bills that died.
- Plan Hillsborough: Plan Amendments, City of Tampa Plan Amendment Procedures Manual, and Hillsborough County Plan Amendment Procedures Manual. Thresholds, filing deadlines, and refiling limits.
- Orange County: Future Land Use Amendments and application schedule (updated July 31, 2026). Local threshold, fees, and 2026 timelines.
- Central Florida Public Media, July 30, 2025 and September 29, 2026. The state's null and void finding, the readoption, and the opt-out.
- City of Miami: Envision 2035/2045. A state coordinated review timeline.
- Chapter 2012-245, Laws of Florida and Broward County Planning Council: Applications, Deadlines and Fees. Countywide plan layers in Pinellas and Broward.
Related reading
- Future Land Use vs. Zoning: What's the Difference?
How a future land use designation differs from a zoning district, how the two fit together, what happens when they conflict, and when a project needs a plan amendment as well as a rezoning, with examples from Florida, Arizona, Texas, and Michigan.
- What Is a Future Land Use Map? FLUM Designations Explained
What a future land use map is, what a future land use designation controls, how the map differs from the zoning map, and how Tampa, Orange County, Pinellas County, Phoenix, and Austin publish theirs.
- What Is a Comprehensive Plan? General Plans and Master Plans Explained
What a comprehensive plan is, what goes in one, how the comprehensive plan map controls zoning, why it is also called a general plan or master plan, and how Tampa, Orange County, Phoenix, Austin, and Pinellas County handle theirs.
- How Long Does Rezoning Take? Published Timelines From 15 US Cities and Counties
Official rezoning timelines from Austin to Seattle, the notice periods and decision deadlines state law sets, what makes a rezoning take longer, and when an approved rezoning actually takes effect.
- Florida Live Local Act Explained: What It Lets You Build on Commercial and Industrial Land
How Florida's Live Local Act lets qualifying affordable multifamily and mixed-use projects go on commercial, industrial, and mixed-use land without a rezoning, with the density, height, and approval rules as amended through July 2026.